The Kentish Flats Offshore Wind Farm is a wind farm located off the coast of Kent, England on a large, flat and shallow plateau just outside the main Thames shipping lanes. The wind farm is operated by Vattenfall.

Kentish Flats Offshore Wind Farm
Vestas V90 Wind Turbine Kentish Flats
Map
CountryEngland, United Kingdom
LocationNorth Sea off the coast of Kent, South East England
Coordinates51°27′36″N 1°5′24″E / 51.46000°N 1.09000°E / 51.46000; 1.09000
StatusOperational
Construction began
  • August 2004
Commission date2005
Owner(s)Vattenfall
Wind farm
TypeOffshore
Max. water depth3–5 m (10–16 ft)
Distance from shore5.5 mi (8.9 km)
Hub height70 m (230 ft)
Rotor diameter90 m (300 ft)
Site area10 km2 (3.9 sq mi)
Power generation
Units operational45
Make and modelVestas V90-3MW / V112-3.3MW
Nameplate capacity139.5 MW
Capacity factor30%
External links
CommonsRelated media on Commons
Map
Wind farm layout

Location

The distance from the nearest wind turbine to Whitstable is 6.2 miles (10.0 km). The nearest turbine is 5.5 miles (8.9 km) away from Herne Bay.

Installation

Turbines at Kentish Flats, Kent, England, with the WWII gun platforms visible towards the right.
Satellite image of the Thames Estuary with Kentish Flats (pre-extension) bottom left.

Construction was completed in August 2005, with commissioning and testing of all turbines completed by September 2005. The wind farm consists of 30 Vestas V90-3MW wind turbines with a total nameplate capacity of 90 MW.[1] Turbines were installed by the Danish offshore wind farms services provider A2SEA.[2] Between 2007 and 2010, the capacity factor was around 30%.[3] Its levelised cost has been estimated at £66/MWh.[4]

Power is transmitted to shore via three export cables.[5]

Kentish Flats extension

In February 2013 Vattenfall was granted consent to extend the existing Kentish Flats Offshore Wind Farm.[6] 15 turbines each with a capacity of 3.3 MW were installed adding an extra 49.5 MW to the wind farm.[7] Offshore construction began in October 2014 and was operational by December 2015.[7][8]