Kuching Urban Transportation System

The Kuching Urban Transportation System (KUTS) is an under-construction Autonomous Rail Rapid Transit (ART) system network in Kuching, Malaysia. It is the first metro rail system to be built in the state of Sarawak which was touted as one of the methods to ease traffic congestion in the city of Kuching.[2] The project is to be constructed using state funds provided by the Development Bank of Sarawak (DBOS).[2][3][4] The proposed ART lines will connect Kuching to Samarahan and Serian as well as future lines to other parts of Greater Kuching.[5] The Premier of Sarawak, Abang Abdul Rahman Johari Abang Openg had initially promised to build the first Kuching ART soon to avoid rising costs,[6] with Chinese companies offering their expertise to collaborate in the construction.[7]

Kuching Urban Transportation System (KUTS)
Official logo
Official logo
Overview
Native nameSistem Pengangkutan Bandaraya Kuching
OwnerSarawak Metro - Sarawak Economic Development Corporation (SEDC)
LocaleKuching, Samarahan and Serian
Transit typeAutonomous Rail Rapid Transit - Guided bi-articulated bus
Number of lines3
Number of stations35
Websitewww.mysarawakmetro.com/kuts
Operation
Operation will start2026; 2 years' time (2026)[1]
Operator(s)Sarawak Metro
Number of vehicles38
Technical
System lengthFirst phase: 69.9 km (43 mi)

Initial plan - Light Rapid Transit

The proposed construction of a RM10.8 billion Kuching LRT project was expected to commence by 2019 and was scheduled to be operational by 2024.[8] It was proposed that the LRT will use hydrogen fuel cell rolling-stock with a travel speed of 70–140km/h.[9]

The hydrogen fuel cell trains were in line with the state government’s vision to develop a hydrogen economy, as part of its green initiative. Aside from hydrogen-powered trains, Kuching will also be the first city in the country to have hydrogen-powered buses.[10]

Planned routes

On 29 March 2018, the Chief Minister of Sarawak released the routes and stations of three of the six lines with 155.2 kilometers of track[11] to be completed in 2024, while the remaining three lines to be implemented at a later stage.[8] A Government-linked company (GLC) called Sarawak Metro Sdn Bhd[12] has been registered to manage the LRT system.[11]

LineOrigin – DestinationLandmark nearby proposed stationsDistance & Stations
 1  Samarahan LineKota Samarahan to Damai via Sungai Batu,Rembus, Kota Samarahan, Summer Mall, Aiman Mall, INTAN/SALCRA/UiTM, UNIMAS, Sarawak Heart Centre, La Promenade, Riveria, eMart, PPKS, Wisma Wan, Vivacity, Simpang Tiga, Swinburne, Jalan Tabuan, Jalan Central Timur, Police HQ, Hikmah Exchange, Jalan Hashim Jaafar, Medan Raya, Sarawak Stadium, Hospital Sarawak, Bandar Baru Samariang, Mara, Rampangi, Salak, Sg. Batu, Buntal, Santubong, Damai Central62.4 km, 25 stations.
 2  Serian LineSerian to Senari via Siburan,South Depot, Serian, Pasar Baki, Tapah, Beratok, Duranta, Siburan, Seratau, Beverly Park, JPJ, Kota Padawan, Everwin, Penrissen, Kuching Sentral, Kuching International Airport, BDC, Gala City, City One, Simpang Tiga, JPN, The Spring Shopping Mall, Chung Hua Middle School No. 3, Jalan Tun Razak, SMK Pending, Bintawa, Isthmus, Borneo Convention Centre Kuching, Demak Laut, Demak Laut Convention Centre, Senari Port, Bako, Muara Tebas, Deep Sea Port82 km, 25 stations.
 3  City Dispersal LineKuching CityWaterfront, UTC, Jalan Abell, Padungan, Padungan Central, Three Hills Park, Tanah Putih, Pending, Jalan Tun Salahudin, Darul Hana, Wisma Bapa Malaysia, Medan Raya, Jalan Hashim Jaafar, Hikmah Exchange10.8 km, 13 stations.
Proposed route for the Kuching Urban Transportation System in 2018.[13]
Blue: Samarahan Line
Red: Serian Line

Samarahan Line (Line 1)

Station CodeWorking NamePositionLocal
government
Interchange / Notes
 SM0 Rembus (Provisional)At-gradeMPKSRembus Depot, near to Kampung Rembus
 SM1 UniversitiNear to UNIMAS Pintu Timur, walking distance to The Summer Shopping Mall
 SM2 MelabanConnected with Aiman Mall
 SM3 SigitinNear to Wisma SALCRA, Walking distance to UiTM Samarahan
 SM4 UNIMASElevated
 SM5 Heart CentreWalking distance to Sarawak Heart Centre
 SM6 RiveriaWalking distance to La Promenade Mall
 SM7 StutongMBKSNear to The NorthBank by IBRACO
 SM8 Wan AlwiNear to Tabuan Jaya Police Complex
 SM9 VivaConnected with Vivacity Megamall
 IS1 Simpang TigaNear to Wisma Persekutuan Public Carpark, Interchange station with  2  Serian Line
 SM11 Jalan TabuanConnected with The Spring Shopping Mall
 SM12 Jalan Central TimurDBKUNear to Kuching Public Works Department
 SM13 Jalan BadruddinConnected with Sarawak General Hospital
 SM14 Hikmah ExchangeNear to Padang Pasir, Hikmah Exchange

Serian Line (Line 2)

Station CodeWorking NamePositionLocal
government
Interchange / Notes
 SR1 Batu 12/JPJElevatedMPPadawanBatu 12 Depot
 SR2 Kota PadawanNear to 10th Mile Bazaar
 SR3 PenrissenMPKSNear to SMK Wira Penrissen
 SR4 Kota SentosaMPPadawanNear to Sentosa Parade
 SR5 Kuching Sentral MBKSConnected with bus terminal
 SR6 Kuching International Airport Connected to airport terminal
 SR7 Pelita HeightNear to RH Plaza
 SR8 Tun JugahNear to Emporium
 SR9 Near to Swinburne University
 IS1 Simpang TigaNear to Wisma Persekutuan Public Carpark, Interchange station with  1  Samarahan Line
 SR10 Jalan Tun RazakNear to Chung Hua Middle School No.3
 SR11 PendingNear to Puspakom
 SR12 BintawaNear to Bintawa Industrial Estate
 SR13 IsthmusAt-gradeDBKUNear to Borneo Convention Centre Kuching

Shelving

However, on 1 September 2018, the Chief Minister of Sarawak announced that the project has been placed on hold, citing that the funds allocated to the project will instead be used to build basic amenities for Sarawak's rural areas.[14]

Revised plan - Autonomous Rail Rapid Transit (ART)

A guided bi-articulated buses at Yibin ART T1 line.

In July 2019, the Chief Minister of Sarawak said that the LRT project will be built using artificial intelligence (AI) technology which will remove the need for conventional rails and bringing down the cost of the project.[15]

In September 2019, the government of Sarawak ultimately decided to go with China's Automated Rapid Transit (ART) system than LRT due to its more affordable cost where the state transport minister said it will be ready by 2022.[16][17] The ART is a type of guided bus running on batteries. In April 2022, Premier Abang Abdul Rahman Johari Abang Openg disclosed to the Singaporean English daily newspaper, The Straits Times that the ART system will likely consist of 52.6 km of route and is expected to begin construction in the third quarter of the same year, with a projected operational date of 2025.[18]

A prototype of the Kuching ART (guided bi-articulated bus powered by hydrogen) undergoing an engineering run.

In August 2023, the state received its first hydrogen-powered ART vehicle prototype and went through an engineering run for two months until September, where it then went through a proof-of-concept testing in November.[19] As of April 2024, the overall progress of Phase 1 of the Kuching Urban Transportation System is now at 20.65% which includes consultation works, studies and physical works.[20]

Planned routes

On 16 December 2022, the Premier of Sarawak released the Phase 1 integrated transit map of the KUTS project with a 69.9-kilometer route consisting of 3 initial rail lines and a total of 31 stations (with 5 provisional stations) to be completed in stages, with Phase 1 of the Blue Line scheduled to be completed in 2025 while the remaining lines are to be constructed at a later date.[21] Currently, the Green Line has since increased the number of stations from 10 to 14 stations bringing the total number of stations across the Kuching Urban Transportation System to 35 stations.[22] However, they are under halt station status and it is currently unknown whether these will be built alongside the opening of the Green Line in 2027.

LineOrigin – DestinationLandmarks of nearby proposed stationsDistance & StationsTo be completed
 SM  Blue LineKota Samarahan to Hikmah ExchangeRembus, Summer Mall, Aiman Mall, UiTM, SALCRA, Unimas, Sarawak Heart Centre, Riveria, La Promenade Shopping Mall, Stutong, Emart Matang, Wisma Wan, Vivacity Megamall, JPN Kuching, The Spring, Simpang Tiga, Swinburne Sarawak University, Batu Lintang, Kuching Paragon, Sarawak General Hospital, Kuching City Mosque, Hikmah Exchange27.6 km, 14 stations.Phase 1: Q4 2025


Phase 2: Q4 2026

 SR  Red LineKuching Sentral to PendingKuching Sentral, Kuching International Airport, Pelita Height, RH Plaza, GalaCity, CityOne Simpang Tiga, JPN Kuching, Jalan Tun Razak, Pending12.3 km, 8 stations.Q4 2026
 DM  Green LinePending to Damai SentralPending, Bintawa, Darul Hana, Wisma Bapa Malaysia, Menara Pelita, Stadium Sarawak, Yayasan Sarawak, Bandar Baru Samariang, Sungai Batu, Santubong, Damai Sentral30 km, 14 stations.Q4 2027

Notes

  1. Bold text denotes that the particular landmark is near the area proposed to be a train depot station.

Blue Line alignment

Station CodeWorking NameLocal
government
Notes / Interchange
Phase 1 (Q4 2025)
 SM00P RembusMPKSProvisional station. Rembus Depot, near to Kampung Rembus, SK (A) Ibnu Khaldun
 SM01 UniversitiNear to Taman Desa Ilmu, walking distance to Pintu Timur UNIMAS, The Summer Shopping Mall
 SM02 MelabanConnected with Aiman Mall
 SM03 SigitinConnected with Wisma SALCRA, walking distance to INTAN
 SM04 UNIMASConnected with UNIMAS Main Gate, walking distance to Everwin Centre
 SM05 Sarawak Heart CentreWalking distance to Sarawak Heart Centre, Eden-on-the-Park, Samarahan Country Club, future Interchange station with a future line
 SM06 RiveriaConnected with La Promenade Mall
Phase 2 (Q4 2026)
 SM07 StutongMBKSConnected with The Northbank, walking distance to Avona Residence, Tunku Putra - HELP International School
 SM08 Wan AlwiWalking distance to Lodge International School, connected to Tabuan Jaya Police Housing Complex
 SM09 Vivacity MallConnected with Vivacity Megamall, walking distance to Milan Square
 SM10  SR10 Simpang TigaWalking distance to Wisma Persekutuan, Kenyalang Park Post Office, Interchange station with the  SR10  Red Line
 SM11 The SpringConnected with The Spring Shopping Mall, ST3 Shopping Mall, Citadines Uplands Hotel, walking distance to Masjid Darul Ittihaad Kenyalang Park
 SM12 Batu LintangDBKUWalking distance to Kuching Public Works Department, Batu Lintang Food Court, Wisma Saberkas
 SM13 Sarawak General HospitalConnected with Sarawak General Hospital, walking distance to SMK Green Road, future Interchange station with a future line
 SM14 Hikmah ExchangeConnected with Hikmah Exchange, walking distance to Padang Pasir, Kuching City Mosque, Wisma Hopoh, future Interchange station with a future line

Red Line alignment

Station CodeWorking NameLocal
government
Notes / Interchange
 SR05 Kuching Sentral MBKSConnected with bus terminal, future Interchange station with a future line
 SR06 Kuching International Airport Connected to airport terminal
 SR07 Pelita HeightNear to RH Plaza
 SR08 Tun JugahNear to Emporium
 SR09 SwinburneNear to Swinburne University
 SR10  SM10 Simpang TigaWalking distance to Wisma Persekutuan, Kenyalang Park Post Office, Interchange station with the  SM10  Blue Line
 SR11 Jalan Tun RazakNear to Chung Hua Middle School No.3
 SR12  DM01 PendingNear to Puspakom, Interchange station with the  DM01  Green Line

Green Line alignment

Station CodeWorking NameLocal
government
Notes / Interchange
 DM01  SR12 PendingMBKSNear to Puspakom, Interchange station with the  SR12  Red Line
 DM02P Darul HanaDBKUProvisional station. Near to Darul Hana
 DM03 Wisma Bapa MalaysiaNear to Wisma Bapa Malaysia
 DM04 Menara PelitaNear to Menara Pelita
 DM05 StadiumNear to Sarawak State Stadium
 DM05AP WaterfrontProvisional station. Near to Waterfront
 DM06P Yayasan SarawakProvisional station. Near to Yayasan Sarawak, future Interchange station with a future line
 DM07 Bandar Baru SamariangNear to Bandar Baru Samariang
 DM07AP Pasir PanjangProvisional station. Near to Pasir Panjang
 DM08 Sungai BatuHalt station. Sungai Batu Depot.
 DM08AP Cove 55Provisional station. Near to Cove 55
 DM09 SantubongHalt station. Near to Santubong
 DM09A Damai Golf CourseHalt station. Near to Damai Golf Course
 DM10 Damai SentralNear to Damai Sentral

Operation facts

  • Project Proponent: Sarawak Metro Sdn Bhd
  • Line Length (km): Line 1 : 28.1 km (67% Elevated), Line 2 : 24.5 km (96% Elevated)
  • Stations: Line 1 : 13 + 1 (provisional), Line 2 : 12
  • Interchange : 1
  • Depot: Line 1 : Rembus Line 2 : Batu 12
  • Operating Speed: Average 35 km/h, Maximum 70 km/h
  • Operating Hours: 6.00 am – 12.00 am
  • Journey Time: Line 1: 38 minutes, Line 2: 40 minutes
  • System: Hydrogen Powered Automated Rapid Transit (ART)
  • Features: Trackless, Runs on rubber tyres. Dedicated lane

See also

References