Line 2 (Mumbai Metro)

Line 2 (Yellow Line) of the Mumbai Metro is a rapid transit metro line in the city of Mumbai, Maharashtra, India. The line connects Dahisar in the northwest with Mandale in Mankhurd via Andheri, BKC and Chembur in the east. Phase One of Line 2A was partially opened on 2 April 2022 from Dahisar East to Dahanukarwadi.

Line 2 (Yellow Line)
BEML Rolling stock of Mumbai Metro Line 2
Overview
Status
  • Line 2A (Operational)[1]
  • Line 2B (Under Construction)
OwnerMMRDA
LocaleMumbai, Maharashtra, India
Termini
Stations17
WebsiteLine 2A
Line 2B
Service
TypeRapid Transit
SystemMumbai Metro
Operator(s)Maha Mumbai Metro Operation Corporation Limited (MMMOCL)
Depot(s)Charkop (2A)
Mandale (2B)
Daily ridership212,000 (July 2023)[2]
History
CommencedNovember 2016 (2016-11)
Opened2 April 2022; 2 years ago (2022-04-02)
Technical
Line length18.589 km (11.551 mi)
Number of tracks2
CharacterGrade-separated, Elevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification25 Kv AC Overhead catenary
Route map

Line 2
0.0000
Dahisar East Line 7 and Line 9
Mahatma Gandhi Road
0.7110
Anand Nagar
Western line Left arrow Dahanu Road and Churchgate Down arrow
2.4227
Kandarpada
3.3831
Mandapeshwar
4.4684
Eksar
5.5375
Borivali West
6.4659
Pahadi Eksar
7.5718
Kandivali West
8.2003
Dahanukarwadi
Charkop Depot
9.5355
Valnai
10.8460
Malad West
12.2434
Lower Malad
13.1831
Bangur Nagar
14.4555
Goregaon West
15.4687
Oshiwara
Adarsh Nagar Line 6
16.4330
Lower Oshiwara
17.5786
Andheri West
D N Nagar Line 1
18.6376
ESIC Nagar
20.3026
Prem Nagar
20.8292
Indira Nagar (Vile Parle)
21.9025
Nanavati Hospital / Up arrow towards Dahanu Road
23.5094
Khira Nagar and Santacruz on Western line
24.4660
Saraswat Nagar
25.5590
National College (Bandra)
26.6997
Bandra and Bandra on Western line
Left arrow towards Churchgate
28.9139
Income Tax Office (BKC) Line 3
Vakola Nala
30.1880
ILFS, BKC
30.8928
MTNL, BKC
32.7202
SG Barve Marg
Central line Left arrow CSMT and Kalyan Right arrow
Lokmanya Tilak Terminus Flyover Road
Harbour line Left arrow CSMT and Panvel Down arrow
34.3492
Kurla (East)
Line 4
35.3563
Eastern Express Highway
35.9967
Chembur
VNP and RC Marg Junction
on Mumbai Monorail
36.9590
Diamond Garden
37.8190
Shivaji Chowk (Chembur)
38.9396
BSNL, Govandi
Up arrow towards CSMT
40.5467
Mankhurd and Mankhurd on Harbour line
Right arrow towards Panvel
41.5074
Mandala
Mandala Depot

Construction on the first section of the line, called Metro 2A (between Dahisar and D.N. Road), began in November 2016, and was completed in April 2022. This section shall be 18.589 km (11.551 mi) long, and comprise 17 of the 39 stations that form part of this route. The new 9.5 km (5.9 mi) section of the Yellow Line from Dahanukarwadi to DN Nagar was inaugurated on January 19, 2023, by Prime Minister Narendra Modi.[3]

Planning

Public private partnership with RInfra

A 38.24 km (23.76 mi) long Colaba–Bandra–Charkop line was proposed as Line 2 in the original Mumbai Metro masterplan unveiled by the MMRDA in 2004. A 13.37 km (8.31 mi) long Bandra-Kurla–Mankhurd line and a 7.5 km (4.7 mi) line from Charkop to Dahisar were proposed as Line 3 and Line 4, respectively, in the same plan.[4][5][6] In the updated masterplan, the proposed Charkop–Bandra–Mankhurd and Charkop–Dahisar lines were merged into a single Dahisar–Bandra–Mankhurd line, which would have been 32 km (20 mi) and had 27 stations. This was planned to be the second corridor of the Mumbai Metro. Like Line 1, this corridor was also proposed to be constructed on a public private partnership (PPP) model.[7]

Then President Pratibha Patil launched the project in August 2009. The MMRDA appointed Reliance Infrastructure (RInfra), in consortium with SNC Lavolin Inc. Canada and Reliance Communication,[8] through an international competitive bidding process to carry out this phase of the project, and the concession agreement was signed with the RInfra-led consortium in January 2010.[9] The project was proposed to be implemented on build–operate–transfer (BOT) basis for a concession period of 35 years with an extension clause of another 10 years.[8] The MMRDA estimated the project would cost 8,250 crore (US$990 million), while Reliance Infrastructure estimated it would cost 11,000 crore.[10] Construction was planned to begin in August 2010 and conclude by mid-2013.[11] However, construction work had yet to begin by December 2012, leading to calls for Line 2 to be cancelled outright.[9]

The line's construction was handicapped by the lack of available land for carsheds at Charkop and Mankhurd; Coastal Regulation Zone (CRZ) laws forbade construction on the land that had been selected by the MMRDA. The Union Ministry of Environment and Forests (MoEF) refused to give clearance for the depots.[12] MMRDA officials plan to solve the problem by shifting the location of the proposed rake depot to Malwani near Malad. The 19 hectares (0.19 km2) plot does not come under the purview of the CRZ laws and therefore will not require environmental clearances.[13] The MMRDA has said that they have not ruled out an underground line, claiming that they had considered a combination of an elevated and underground alignment but had deemed it impossible due to the large land requirement for ramps and slip roads.[14]

On 6 September 2012, the MMRDA sent a letter to Reliance Infrastructure asking them to start work on the metro immediately or face legal action.[15][16] In response to the letter, RInfra blamed the government and MMRDA for the delayed construction work. They said that the government had failed to fulfill its contractual obligation to provide the necessary land, right of way permits and clearances.[17][18][19][20] On 8 February 2013, then RInfra CEO Sumit Banerjee claimed that the project had not advanced because the MMRDA had failed to fulfill its share of the responsibilities.[21][22] The state government had since been considering alternative sites for the depot, which might have led to complete change in the alignment of the line and could have required re-bidding for the project.[23] On 9 August 2013, DNA reported that an MMRDA official had informed them that a 27-acre (11 ha) plot that was to be used as the casting yard for Line 2, was planned to be marked for use as a casting yard for Line 3. The paper called the move "a clear indication" that Line 2 "will not take off in the near future."[24] Chief Minister Prithviraj Chavan told the media on 30 August 2013 that "it is now clear that Mumbai's Metro II project will now not happen."[25][26]

On 13 November 2014, Reliance Infrastructure announced that it had terminated the agreement between the MMTPL and the Maharashtra government. RInfra stated, "Due to non-fulfilment of various critical obligations by Maharashtra government and Mumbai Metropolitan Region Development Authority (MMRDA), the project could not take off. Even after four years, despite the best efforts of the Maharashtra government, various project impediments could not be resolved." The MMRDA issued a statement confirming that the agreement was terminated with mutual consent. No party will bare any cost as a result of the termination and the state government will return a bank guarantee of 160 crore. The MMRDA also clarified that the Line 2 project had not been cancelled and will be constructed by the Mumbai Metro Railway Corp. Ltd (MMRCL) under an engineering, procurement and construction (EPC) model.[27][28]

EPC model

In September 2013, the MMRDA appointed RITES to study the feasibility of constructing the proposed 32 km (20 mi) metro line underground. RITES also studied the feasibility of extending the corridor and merging the 7.5 km (4.7 mi) Charkop-Dahisar metro, proposed as a separate line, with this project. RITES submitted its final report to the MMRDA in the last week of May 2014, concluding that constructing the metro underground and extending it up to Dahisar was feasible.[29][30][31] The merged Dahisar-Bandra-Mankhurd line would be 40.2 km (25.0 mi) long and have 37 underground stations. The estimated cost of construction of this line was 28,900 crore, 134% higher than the originally estimated costs of 7,660 crore for the Charkop-Bandra-Mankhurd line and 4,680 crore for the Charkop-Dahisar corridor. RITES proposed the construction of a major car depot at Oshiwara and a minor car depot at Mandale, Mankhurd on sites that were a mix of publicly and privately held land.[32] The extension of the line to Mankhurd was proposed to resolve land acquisition issues as land was available for the construction of a depot at Mankhurd.[33]

In June 2015, the MMRDA proposed building an 18.6 km line from Dahisar East to Andheri East, and a 12 km line from Bandra Kurla Complex to Mankhurd as part of a plan to build 6 new metro lines at a total estimated cost of 64,000 crore (US$7.7 billion).[34] The MMRDA approved the detailed project report for the line in August 2015. The report estimated the cost of the project as 12,000 crore (US$1.4 billion).[35] On 15 June 2015, the MMRDA announced that it would combine the two stretches and implement Line 2 of the Mumbai Metro in three parts - Dahisar East-DN Nagar (Metro 2A), DN Nagar-BKC (Metro 2B), and BKC-Mankhurd (Metro 2C).[36][37] On 1 July 2015, it was announced that the MMRDA was allotted a 22-acre (8.9 ha) plot in Mankhurd adjacent to the Sion Panvel highway for the Metro carshed. The land was under dispute between the MMRDA and the State Home Ministry for the construction of a Jail.[38]

The plan was later modified to build the line in two sections - Dahisar-DN Nagar (Metro 2A) and DN Nagar-Mankhurd (Metro 2B). Metro 2A was approved by the Maharashtra Government on 6 October 2015.[39] In November 2015, the Department of Economic Affairs (DEA) cleared the MMRDA's request to secure a loan from the Asian Development Bank (ADB).[40] The Maharashtra Cabinet approved the Metro 2B corridor on 27 September 2016. Half of the project cost will be funded by the Centre and the State Government, while the remaining will be financed through loans from the Asian Development Bank and New Development Bank. The Metro 2B corridor was proposed to be 23.5 km (14.6 mi) long and have 22 stations. The project was estimated to cost 10,986 crore,[41][42] including land acquisition cost of 1,274 crore.[33]

In February 2020, MMRDA metropolitan commissioner R.A. Rajeev stated that Line 2 would be identified as the Yellow Line.[43] A study by World Resources Institute (WRI) India, published in May 2021, estimated that Metro 2A and Line 7 had the potential to create 1.1 million jobs in the city.[44]

Elevated Metro 2B

The elevated Metro 2B line received permission from Central Railway (CR) to be built at a height of 22 metres over the Central Line to accommodate CR's plan to construct an elevated CST-Panvel high-speed rail line and an elevated CST-Kalyan line. The MMRDA objected to the height band due to concerns over difficulty involved in operating a metro line at that height as well as evacuating passengers to ground level in case of an emergency. The Central Railway later granted the MMRDA permission to build Metro 2B at a height of 13 metres, with the CST-Panvel elevated line proposed to take a height of 22 metres.[45]

The plan to build Metro 2B as an elevated corridor faced opposition. Residents of SV Road gathered at the Sacred Heart Boys’ School in Khar to protest the Metro 2B project on 12 August 2017.[46] Petitions against the project were also filed in the Bombay High Court by the Juhu Vile Parle Development Cooperative Housing Association, the Gulmohar area society welfare group, and the Balabhai Nanavati Hospital.[47] Some Mumbai residents protested the project on 5 October 2017 at Santacruz and Mahim.[48][49] Several celebrities including Javed Akthar participated in the protest.[50] Metro 2B also faced legal issues concerning the section between Indira Nagar and Nanavati Hospital that passes through a funnel area of the Juhu Aerodrome.[51][52]

In June 2018, the MMRDA filed an affidavit in the Bombay High Court stating that it had "taken into consideration all the aspects of the project, including the pros and cons of underground and elevated Metro, and have taken a conscious decision to go for elevated Metro". The agency stated that there was insufficient land available to build the metro partly underground as large quantities of land were required to build the ramps going underground and coming back overground. The agency also noted that an underground metro would take 2 years to build and would cost over 5.5 times more per kilometer than an elevated line. The MMRDA stated that the design of the metro was a "highly technical issue" and that the petitioners did not have the required scientific experience to evaluate it.[47][53] In August 2019, the Court directed the petitioners to explain why they thought the MMRDA had selected an elevated line instead of an underground line, after the petitioner's advocate stated that he "had not come prepared" and did not know if there was a scientific reason behind the MMRDA's decision.[54] The Bombay High Court ruled in favour of the MMRDA and dismissed all petitions against the Metro 2B project.[55][56][57]

Cancelled stations

Two metro stations (MMRDA station and Kurla Terminus) that were originally proposed for Metro 2B were cancelled. The MMRDA Station was cancelled because it overlapped with the Kalanagar flyover ramp. The Kurla Terminus station was cancelled in September 2020 because it was in the path of the restricted funnel zone for Mumbai Airport. Further, the proposed SG Barve Marg station was only 474 metres away from the proposed Kurla Terminus. Another issue was that the Kurla Terminus station would have been located in between the Santa Cruz–Chembur Link Road (SCLR) rail overbridge and another permanent structure.[58][59]

Line 7 of the Mumbai Metro connects Dahisar East with Andheri East, and the depot for the line was proposed to be located at Dahisar.[60] However, land acquisition for the Dahisar depot was delayed by litigation filed in 2016. In 2020, the MMRDA proposed using the depot at Charkop to serve both Line 2A and Line 7 by building a ring metro line to connect the two corridors. The MMRDA utilized an empty plot of land located after Ovaripada station on Line 7 to build pillars for the link connecting the two lines.[61][62] In November 2021, the MMRDA cancelled the plan to build the depot at Dahisar and instead proposed building the depot for Lines 7, 7A and 9 at Rai Murdhe in Bhayandar.[63]

Line 2A and Line 7 were both commissioned on 2 April 2022, with services operating between Dahanukarwadi and Aarey via Dahisar East. Both lines were extended on 19 January 2023, providing circular service between Andheri West and Gundavali via Dahisar East.[64] The Charkop depot currently serves as the depot for Line 2A and Line 7. The Mandale depot will be used to serve Lines 2A and 2B once completed.[65]

Construction

Line 2 will be built in two sections - Dahisar-DN Nagar (Metro 2A) and DN Nagar-Mankhurd (Metro 2B). The MMRDA signed an agreement with the DMRC, appointing the latter as the implementing agency for the project on 12 December 2015.[66] The DMRC was paid 334 crore (US$40 million) for its services.[67] The DMRC will have sole responsibility for civil and technical works and operations and maintenance on the Metro 2A corridor. For the Metro 2B corridor, the MMRDA will carry out civil works, while the DMRC is tasked with technical work and operations and maintenance.[68] In July 2018, the state government granted special planning authority status to the MMRDA in a bid to speed up implementation of metro projects.[69]

History
SectionExtension dateTerminiLengthStations
Metro 2A[70]2 April 2022Dahisar EastDahanukarwadi9.8 kilometers (6.1 mi)9
19 January 2023DahanukarwadiAndheri West8.8 kilometers (5.5 mi)8
Metro 2B[71]2024[72]ESIC NagarMandale23.643 kilometers (14.691 mi)20
42.232 kilometers (26.242 mi)37

Metro 2A

Metro 2A is 18.589 km (11.551 mi) long and connects Dahisar East to DN Nagar with 17 stations.[33] Prime Minister Narendra Modi laid the foundation station for Metro 2A on 11 October 2015.[73] The DMRC floated two tenders for the designing and construction of the corridor. The first package included the design and construction of a viaduct and 9 stations from Dahisar East to Dahanukarwadi, and the second package included the remaining viaduct and 8 stations from Valnai to Andheri West. J Kumar Infra Projects Limited was awarded both packages in June 2016, and carried out civil work, including viaducts and stations. The cost of the contract was 1,300 crore (US$160 million), with J Kumar Infra bidding below the reserve price.[74][75]

Soil testing work along the corridor commenced in July 2016.[76] Construction on the corridor began in November 2016.[77] The corridor was scheduled to be commissioned in October 2019, but delays in procuring rolling stock and issues with civil works pushed the deadline to December 2020.[77] The opening of the line was further delayed by the COVID-19 pandemic.[78] As of 13 September 2017, 77% of the soil investigation work for pier foundation, 76% of barricading work, 37% piles, and 19% pile caps were completed, and 110 piers were cast, 75 pier caps erected, 26 U girders erected and work pile foundation work commenced for all 17 stations.[77] In April 2019, the MMRDA issued tenders for the rooftop solar PV power projects at stations on Metro 2A.[79] Track laying work on the line began in June 2019.[80]

Shimpoli station under construction in Borivali in 2022

The stations on the line have a platform length of 185 metres to serve 8 car rakes. Stations were built on a single pier, unlike the three piers used to support stations on Line 1. The single pier design was chosen due to lack of space available for construction on New Link Road. Unlike most metros in India, the stations were not completely constructed on site. Construction utilized "pi-girders" which were pre-cast at a casting yard in Bandra. The girders were then erected onto the station for platforms.[81] Most of the spans on the line have a length of 25–28 metres. A 51 metre long steel girder was installed on New Link Road in Kandivali to accommodate a 700 metre radius curve along the line.[82]

MMRDA metropolitan commissioner R.A. Rajeev stated in September 2020 that almost 80% of construction work had been completed.[83] The MMRDA began conducting pre-trials on the rolling stock at the Charkop depot in February 2021.[84] The MMRDA announced that electrification of the line had been completed on 26 May, and the first trial runs were conducted from 31 May.[85][86] The MMRDA began a dynamic test and trial run on the 20 km stretch between Dhanukarwadi and Aarey (including a portion of Line 7) on 19 June.[87] The final I-girder on Line 2A was launched at Adarsh Nagar Junction in Andheri on 6 October 2021.[88] The stretch between Dhanukarwadi and Aarey received provisional approval from the Research Designs and Standards Organisation (RDSO) in January 2022.[89] The Commissioner of Metro Rail Safety (CMRS) began inspecting the line in February 2022.[90]

A section of Metro 2A from Dhanukarwadi to Dahisar East (along with the section of Line 7 from Dahisar East to Aarey) was opened on 2 April 2022. Chief Minister Uddhav Thackeray flagged off the first train at 4pm in the presence of Deputy Chief Minister Ajit Pawar, Urban Development Minister Eknath Shinde, NCP chief Sharad Pawar and the Leader of Opposition in the Legislative Council, Pravin Darekar. The line opened for public service from 8pm, with services operating between Dahanukarwadi and Aarey (on Line 7) via Dahisar East.[91]

The remaining section of Metro 2A from Dhanukarwadi to DN Nagar received approval from the RDSO in October 2022.[92] The CMRS began inspecting the line in December 2022.[93] The final section of the line (along with the final section of Line 7 from Goregaon East to Gundavali) was inaugurated on 19 January 2023 by Prime Minister Narendra Modi.[94][95]

Metro 2B

Metro 2B is 23.643 km (14.691 mi) long and connects DN Nagar to Mankhurd with 20 stations.[45] The foundation stone for Metro 2B was laid by Prime Minister Narendra Modi on 24 December 2016.[96] The MMRDA utilized a drone to carry out survey work for Metro 2B. The drones were fitted with a 360-degree camera that provides up to 3 millimeter accuracy. The aerial survey takes less time than a regular survey, achieves greater accuracy and helps protect against false claims for compensation.[97] The MMRDA invited bids for civil work on Metro 2B on 4 January 2017.[98][99] Metro 2B was divided into four packages - ESIC Nagar to Khira Nagar, Saraswat Nagar to ILFS, MTNL Metro to Chembur, and Diamond Garden to Mandale.[100] Metro 2B was tendered alongside Metro 4. L&T, Afcons Infrastructure, Tata, NCC and JMC, Reliance Infrastructure-RdE, JKumar Group, ITD Cementation, CHEC-TPL bid for packages on both Metro 2B and Metro 4. Simplex Infrastructure and a consortium of GHEC-RCC-JV-China placed bids only for some packages of Metro 2B. A total of 10 firms and/or consortia submitted bids for the two lines.[101][102] The MMRDA shortlisted 8 bidders for the contract to build the Mandale depot in November 2017.[103]

Simplex Infrastructure was awarded a 1,080 crore (US$130 million) to build the first package of Metro 2B by the MMRDA on 13 November 2017. This included the design and construction of a 12 km long viaduct and 11 elevated stations including ESIC Nagar, Prem Nagar, Indira Nagar, Old Airport, Khira Nagar, Saraswat Nagar, National College, Bandra (W), MMRDA Office, Income Tax Office and BKC.[104][105] A joint venture between RCC Infra Ventures and MBZ-Ukrain was awarded a 521 crore (US$62 million) contract for the second package on 3 March 2018. This included the design and construction of a 5.9 km long elevated viaduct, the Mandale car depot, and 6 metro stations including MTNL Metro, SG Barve Marg, Kurla Terminus, Kurla East, and Chembur.[106] Construction began in April 2018.[107] In March 2019, the MMRDA altered the alignment of the proposed route at BKC Road to avoid it passing in front of Shiv Sena president Uddhav Thackeray's residence.[108]

On 4 February 2020, the MMRDA terminated the contract awarded to Simplex Infrastructure and the RCC-MBZ joint venture over delay in completing the work. Simplex had completed 5% of the total work in 30 months, while it was scheduled to have completed 65%.[109][110] RCC-MBZ had only completed 4.46% of total work.[111] The MMRDA awarded a 1,307.88 crore (US$160 million) to J Kumar Infraprojects to complete work on the first package in June 2021,[112][113] and a 760 crore (US$91 million) contract to Nagarjuna Construction Company to complete work on the second package of Metro 2B in March 2022.[114][111] Construction resumed in March 2023.[115][116] The MMRDA stated that 70% of work on the Mandale depot had been completed by the end of May 2023.[117]

Current status

Metro 2B

Sr. No.Name of WorkDescriptionStatus as of [118]
21 May 201922 November 20194 August 202015 September 20205 October 20204 January 20212 August 202127 January 20225 September 202225 September 2023
1Soil Investigation WorksSoil investigation work for pier foundation completed55%59.08%68.60%70.60%72.86%74.29%82.86%90.57%100.00%
2Utility WorksWork completed23%28.86%40.22%45.07%45.25%46.46%57.21%65.21%94.31%
3Piling WorksPiling work for foundations completed7%8.84%23.15%25.10%26.62%28.20%33.95%38.08%49.46%80.88%
4Pile Cap WorksPile Cap work completed3%4.08%12.1%12.4%12.93%16.15%20.67%30.96%37.28%79.18%
5Pier WorksPiers Cast1.2%1.45%5.95%6.73%6.94%14.25%23.46%33.31%63.48%
6Pier Cap WorksCastingCasting beds are under preparation.3.12%3.92%5.52%6.60%12.91%24.36%68.09%
Erection1.88%2.33%2.39%5.14%10.85%21.27%59.47%
7U Girder WorksCasting0.7%0.8%6.22%7.84%7.91%10.79%11.96%34.48%58.08%
ErectionCasting yard works are in progress1.40%1.64%1.98%3.93%7.7%20.69%40.00%
8Station WorkWork is in progress at out of 22 stationsYet to startSoil Investigation and Utility Identification work is in progress. Foundation work yet to startFoundation (Pile and Pile Cap) work is in progress at 5 no's of stations. Substructure work yet to start.Foundation (Pile and Pile Cap) work is in progress at 5 no's of stations.
9Mandale Depot worksWork completed7.00%11.15%21.22%40.06%80.72%

Stations

Passenger information display and platform screen doors at Kandarpada station.

There will be a total of 37 stations on Line 2. Metro 2A, from Dahisar to Andheri West, has 17 stations. Metro 2B, from DN Nagar to Mankhurd, will have 20 stations.[119][120] The MMRDA partnered with bike-sharing app MBYK to provide a bicycle-sharing service at stations on the line.[121]

Yellow Line 2
#Station NameOpeningConnectionsAlignment
EnglishMarathi
1Dahisar Eastदहिसर पूर्व2 April 2022Line 7
and Line 9 (Under Construction)
Elevated
2Anand Nagarआनंद नगर2 April 2022NoneElevated
3Kandarpadaकंदरपाडा2 April 2022NoneElevated
4Mandapeshwarमंडपेश्वर- आयसी कॉलनी2 April 2022NoneElevated
5Eksarएकसर2 April 2022NoneElevated
6Borivali Westबोरिवली पश्चिम2 April 2022NoneElevated
7Shimpoliशिंपोली2 April 2022NoneElevated
8Kandivali Westकांदिवली पश्चिम2 April 2022NoneElevated
9Dahanukarwadiडहाणूकरवाडी2 April 2022NoneElevated
10Valnai–Meeth Chowkyवळनई-मीठ चौकी19 January 2023NoneElevated
11Malad Westमालाड पश्चिम19 January 2023NoneElevated
12Lower Maladलोअर मालाड19 January 2023NoneElevated
13Bangur Nagarबांगूरनगर19 January 2023NoneElevated
14Goregaon Westगोरेगाव पश्चिम19 January 2023NoneElevated
15Oshiwaraओशिवारा19 January 2023NoneElevated
16Lower Oshiwaraलोअर ओशिवरा19 January 2023Line 6 (Under Construction)Elevated
17Andheri Westअंधेरी पश्चिम19 January 2023Line 1Elevated
18ESIC Nagarका.रा.वि.म. नगरUnder ConstructionNoneElevated
19Prem Nagarप्रेम नगरUnder ConstructionNoneElevated
20Indira Nagar (Vile Parle)इंदिरा नगर (विले पार्ले)Under ConstructionNoneElevated
21Nanavati Hospitalनानावती रुग्णालयUnder ConstructionNoneElevated
22Khira Nagarखीरा नगरUnder ConstructionSantacruz on Western lineElevated
23Saraswat Nagarसारस्वत नगरUnder ConstructionNoneElevated
24National College (Bandra)राष्ट्रीय महाविद्यालय (वांद्रे)Under ConstructionNoneElevated
25Bandraवांद्रेUnder ConstructionBandra on Western lineElevated
26Income Tax Office (BKC)आयकर कार्यालय (बीकेसी)Under ConstructionLine 3 (Under Construction)Elevated
27ILFS, BKCआयएलएफएस, बीकेसीUnder ConstructionNoneElevated
28MTNL, BKCएमटीएनएल, बीकेसीUnder ConstructionNoneElevated
29SG Barve Margएसजी बर्वे मार्गUnder ConstructionNoneElevated
30Kurla (East)कुर्ला (पूर्व)Under ConstructionNoneElevated
31Eastern Express Highwayपूर्व द्रुतगति महामार्गUnder ConstructionLine 4 (Under Construction)Elevated
32ChemburचेंबूरUnder ConstructionChembur station on MonorailElevated
33Diamond Gardenडायमंड गार्डनUnder ConstructionNoneElevated
34Shivaji Chowk (Chembur)शिवाजी चौक (चेंबूर)Under ConstructionNoneElevated
35BSNL, Govandiबी.एस.एन.एल, गोवंडीUnder ConstructionNoneElevated
36Mankhurdमानखुर्दUnder ConstructionNoneElevated
37MandaleमंडलेUnder ConstructionNoneElevated

Cost

Metro 2A was built at a cost of 6,410 crore (US$770 million). The line was originally scheduled to open in October 2019, but was delayed, and completed in January 2023. The MMRDA stated that the delay escalated the project cost by about 7%.[78] The State Government bore 48% of the total project cost. The MMRDA secured a loan worth 52% of the total project cost from the Asian Development Bank (ADB).[40] The MMRDA allotted 340 crore (US$41 million) to the DMRC to implement and commission rolling stock, signalling and telecommunication work for the Metro 2A and Line 7 corridors on 26 November 2016.[122][123][124]

Metro 2B is estimated to cost 10,986 crore,[41][42] including land acquisition cost of 1,274 crore.[33] Half of the project cost will be funded by the Centre and the State Government, while the remaining will be financed through loans from the Asian Development Bank and the World Bank.

On 2 March 2019, the Union Ministry of Finance stated that it signed a $926 million loan agreement with the ADB to fund construction of Lines 2 and 7. This was the single largest infrastructure loan ever extended by the ADB. The funds will be used to procure 63 six-car trainsets and for signalling and safety systems on both corridors.[125]

Infrastructure

Rolling stock

BEML was awarded a 3,015 crore (US$360 million) contract to supply 378 metro cars (63 trainsets) for Line 2 and Line 7 in November 2018.[126] An additional 126 metro cars (21 trainsets) were ordered from BEML to cater to metro extensions.[127] All trainsets were manufactured at BEML's Rail Coach Factory in Bangalore, Karnataka. The rakes are capable of driverless operation making them the first driverless metro trains to be made in India.[128] BEML began manufacturing the coaches on 29 July 2019,[129] built the first metro coach in 75 days and unveiled it in September 2019.[130] The first trainset arrived in Mumbai on 28 January 2021.[131]

Each trainset is made up of 6 coaches with a total passenger capacity of 1,660 and dense crush load capacity of 2,092. The trainset is 3.2 metres wide, made of stainless steel and each coach has 4 doors on each side. The rake employs a regenerative braking system.[132][127]

Depot

The Charkop depot currently serves as the depot for Line 2A and Line 7.[65] The Charkop depot is located on a 16.40 hectare site,[70] and has 20 stabling lines.[65] The Charkop depot had 305 employees of which 30% were women (as of October 2022).[133]

The depot for Line 2 is proposed to be located on a 28 hectare site at Mandale, and is the largest metro depot in Mumbai. It has a double decker structure with 76 stabling lines.[65] It is currently under construction and will serve Line 2A and 2B once completed.

Signalling

Line 2 utilises the Alstom Urbalis 400 communications-based train control (CBTC) signalling system. Alstom was awarded a EUR90 million contract to supply the signalling and telecommunications systems for Mumbai Metro Line 2 and Line 7, as well as Pune Metro Line 1 and Line 7.[134][135]

Power

Line 2 is electrified at 25 kV 50 Hz AC, with power provided via an overhead catenary. The MMRDA signed an agreement with Adani Electricity Mumbai Limited to supply electricity to Metro 2A and Metro 7 on 2 December 2022. Around 120 million units is required to power both lines.[136][137]

Fare collection

A consortium of Indian company Datamatics and Italian company AEP Ticketing solutions S.R.L was awarded a 160 crore (US$19 million) contract to implement the automated fare collection system for Line 2 and Line 7 in February 2019.[138][139][140]